City Construction Projects Manson Pike/Fortress Blvd Realignment Project
Expected No Lane Closures: Traffic has been shifted onto the newly built section of Manson Pike near the bridge at Overall Creek to Fortress Blvd. Gresham Lane is closed at Medical Center Parkway and traffic to and from Medical Center Parkway is shifted to the new Gresham Lane connector road from Fortress Blvd. Traffic control signs are in-place. Work continues, no lane closures
Fortress Blvd Widening Project (Between Blaze Drive and the new Manson/Fortress Intersection)
Expected No Lane Closures: The traffic has been reduced to two lanes (one lane each direction) on Fortress Blvd between Blaze Drive and Chippewa Place. The work entails the widening Fortress Blvd from a three lane curb and gutter street to a five lane curb and gutter street with bike lanes and sidewalks. Work also includes adding a right turn lane of Blaze Drive adjacent to the elementary school. Street light installation crews will be working on Fortress Blvd between Puckett Street and Blaze Drive. There will be minor traffic interruptions. Work continues, no lane closures
Obrien Drive Sewer Construction Project (Between Bradyville Pike and Winston Place)
Expected Lane Closures: Monday through Friday, 9AM – 3:30 PM: Murfreesboro Water and Sewer Department will continue replacing the sewer main and services along Obrien Drive between Rutherford St and Winston for the next four to five weeks. There will be lane shifts and road closures on Obrien Drive. Detours signs and appropriate traffic controls will be in-place. The road will be opened to local traffic only and the property owners on Obrien Drive have been notified. Work continues, no major changes.
CCTV Monitoring System Project
Expected Lane Closures: Tuesday through Friday, 8:30 AM to 4:00 PM: The contractor for the CCTV expansion project will be installing overhead messenger and fiber optic cables along Memorial Blvd between DeJarnette Lane & Thompson Lane. There will be intermittent moving lane closures and traffic interruptions on Memorial Blvd. Traffic signal crews will be working along SE Broad Street between Mercury Blvd and Main Street. There will be minor traffic interruptions at the signalized intersections.
Maney Avenue Street Improvement Project (between SE Broad Street and College Street) Expected No Lane Closures: Monday through Friday, 8 AM to 4:00 PM: Contractor will begin working on offsite drainage improvements just north of Maney Avenue. There will be no lane closures on SE Broad Street or Maney Avenue.
|
|