The following road projects will affect traffic in Murfreesboro during the week beginning April 27:
Road conditions are shown every hour on Channel 3.
Murfreesboro’s Street Department has started its annual paving campaign. The following projects will be completed this week:
- College Street will be paved from Medical Center Parkway to the CSX underpass. Paving will take place from 9 a.m.-3 p.m. Monday and Tuesday. Weather Permitting.
One lane of traffic will be maintained at all times.
- Repaving Clark Boulevard between Broad and Jones streets will begin Wednesday. Work will be done from 9 a.m.-3 p.m. There will be definite interruptions in traffic. Avoid if possible.
- Beginning May 4, Murfreesboro Water and Sewer Department (MWSD) will begin reconstruction of a sewer main under Vine Street from Maney to Bilbro avenues.
Through traffic, traveling for the east and west will be detoured to Main and Sevier streets. Local residents will have access to homes at all times.
Starting Monday from 9 a.m.-3 p.m., weather permitting, crews will do preliminary work on Vine Street between Highland and Maney. There will be some interruptions in traffic.
- Traffic will be shifted to the east side (the Dodge’s Store side) of Northwest Broad Street at 2 p.m. Sunday, weather permitting.
Two lanes will be available in both directions and a center turning lane between Memorial Boulevard and Vine Street as part of a TDOT bridge replacement project.
Protected left turns will be permitted again at Main Street, but avoid the area if possible.
Message boards are placed around town to direct motorists around the construction. There are no detour routes.
- River Rock Boulevard is still closed from State Route 99 to Stoney Meadow Drive.
Through traffic is detoured from SR 99 onto Athens Avenue to Adonis Drive to Spartan Court to Pecan Ridge Drive to Centertree Drive and back onto River Rock. |